SCIRT Management Plans

A set of Management Plans were developed during SCIRT's lifetime to intentionally guide the organisation. These plans were reviewed annually and updated as required. SCIRT's Programme Management Plan was the overarching plan that listed all the other plans and provided an overview of their contents.
The latest versions of the plans are attached below.
The Initial Alliance Agreement requested an Alliance Management Plan and a minimum of 10 supporting management and operational plans be developed prior to the start of SCIRT:

  1. Quality Plan

  2. Health and Safety Plan

  3. Environmental Plan

  4. Communications and Consultation Plan

  5. Transition Plan

  6. Work Packaging and Delivery Strategy Plan

  7. Procurement Plan

  8. Finance and Administration Plan

  9. Human Resources Plan

  10. Social Impact Plan

Additional plans were subsequently requested under the Alliance Agreement, so in September 2011 the first Management Plan Set was comprised of an overarching Programme Management Plan and 23 supporting plans:
  1. Administration Plan

  2. Asset Investigation Plan

  3. Construction Plan

  4. Design Plan

  5. Emergency Response Plan

  6. Environmental Plan

  7. Estimating Plan

  8. Financial Plan

  9. Health and Safety Plan

  10. Horizontal Infrastructure Rebuild Strategy Plan

  11. Human Resources Plan

  12. IRMO to SCIRT Plan

  13. KRA Plan

  14. Peak Performance Plan

  15. Procurement Plan

  16. Project Prioritisation Plan

  17. Quality Plan

  18. Risk Plan

  19. Schedule Plan

  20. Scope Plan

  21. Stakeholder Plan

  22. Utilities Plan

  23. Value Plan

Six additional plans were subsequently created as needs arose:
  1. The Internal Communication Plan was created in January 2013 in response to the difficulties encountered with communicating to a "virtual" organisation comprised of more than 50 different companies.

  2. The Central City Delivery Plan originated in December 2013 in order to mitigate the issues and risks associated with the infrastructure rebuild within the Central Business District (CBD).

  3. The Crisis Plan was developed in January 2014 to outline the communication response in the event of a major incident.

  4. The Fraud Response Plan was extracted from the Financial Plan and created in August 2014 as a standalone item to outline how to manage suspected fraud.

  5. The Close Down Activities Plan was written in June 2016 to document the wind up process.

  6. The Learning Legacy Plan was created in June 2016 to document the process of identifying and sharing learnings from the establishment and operation of SCIRT.

Last updated
11:30pm 1st November 2017
Type
Collection
Identifier
qsr-collection:21791

Contains 30 items


Health and Safety Management Plan
Health and Safety Management Plan
A plan which aims to ensure an environment of Zero Harm on SCIRT worksites. The first version of this plan was produced on 29 July 2011.
Horizontal Infrastructure Rebuild Strategy Management Plan
Horizontal Infrastructure Rebuild Strategy Management Plan
A plan which defines the strategy underlying the SCIRT rebuild programme.
Human Resources Management Plan
Human Resources Management Plan
A plan which outlines SCIRT's approach to Human Resource Management. The first version of this plan was produced on 30 August 2011.
Internal Communication Plan
Internal Communication Plan
A plan which sets out how SCIRT will carry out internal communication over the life of its programme of work. The first version of this plan was produced on 24 January 2011.
IRMO to SCIRT Transition Management Plan
IRMO to SCIRT Transition Management Plan
A plan which describes how the transition from the IRMO programme to the SCIRT programme will take place after the signing of the Alliance Agreement.
KRA Management Plan
KRA Management Plan
A plan which defines the framework for performance measurement to align SCIRT with the objectives from the Alliance Agreement objectives. The first version of this plan was produced on 20 August 2011.
Learning Legacy Management Plan
Learning Legacy Management Plan
A plan which documents the process SCIRT will follow to identify and pass on learnings from its programme of work. The first version of this plan was produced on 21 June 2016.
Peak Performance Plan
Peak Performance Plan
A plan which provides SCIRT with a map for building and sustaining outstanding performance. The first version of this plan was produced on 18 February 2013.
Procurement Management Plan
Procurement Management Plan
A plan which defines the procurement activities to be applied to SCIRT and explains how those activities are to be undertaken to meet SCIRT objectives and requirements. The first version of this plan was produced on 14 September 2011.
Programme Management Plan
Programme Management Plan
A plan which introduces SCIRT, its management structure and its set of management plans. The first version of this plan was produced on 10 August 2011.
Project Prioritisation Management Plan
Project Prioritisation Management Plan
A plan which describes the framework, principles and process for determining project prioritisation and the sequence in which those projects are carried out. The first version of this plan was produced on 23 September 2011.
Quality Management Plan
Quality Management Plan
A plan which aims to ensure the SCIRT programme complies with set specifications, design and industry quality standards. The first version of this plan was produced on 20 July 2011.